📐 Project Type
ft
ft
in
pcs
Identical pieces only; run different sizes separately
Subgrade is never perfectly flat, so the hole always takes more than the arithmetic says. The cubic-yard figure below stays exact; the order line adds this margin.
🧾 Whole-Slab Materials (optional)
Crushed stone, with 20% added for compaction.
Take the bar size and spacing from your drawing or local code.
Adds the rest of the slab to the results: reinforcement, base, vapor barrier, form boards, stakes and control joints. For slabs, thickened-edge slabs, triangles and round pads.
✓ Results
Volume (cubic feet) 33.3 cu ft
Weight (at 145 lb per cu ft) 4,833 lb (2.4 tons)
1.23 cu yd
Total Cubic Yards
Order with 10% waste 1.36 cu yd
How to buy it Ready-mix is usually cheaper
If you use 80 lb bags 56 bags, 4,480 lb to haul and mix

Pre-Mixed Bags Needed:

40 lb bags
112
50 lb bags
89
60 lb bags
75
80 lb bags
56

Whole-Slab Materials:

Gravel base 1.48 cu yd (2.07 tons) of crushed stone
Reinforcement 3 sheets of 5 ft × 10 ft mesh (6 in laps)
Form boards 40 linear ft of 2x6
Form stakes 18 stakes (one every 3 ft plus one per corner)
Control joints None needed: no panel is over 10 ft

Need a gravel base for your concrete?

Calculate Gravel Needed →

Pouring a slab? Know the area first.

Use our Square Footage Calculator →

How to Calculate Concrete Volume

Slab-on-grade cross-section Cross-section of a concrete slab on grade, from the bottom up: compacted subgrade, 4 inches of compacted gravel base, a 6-mil polyethylene vapor barrier, then a 4-inch concrete slab with reinforcing bar supported on chairs at mid-slab depth. 4 in 4 in Concrete slab 4 in typical for patios and walkways 6-mil vapor barrier interior slabs only Compacted gravel base ordered separately from the slab Compacted subgrade Rebar on chairs, held at mid-slab depth
Fig. 1 — A typical residential slab-on-grade build-up. The 4 in slab thickness is the number you enter in the calculator; the gravel base below it is ordered separately.
Triangle slab worked example A triangle with sides of 12, 10 and 15 feet, with the area worked out by Heron's formula as 59.8 square feet, and the volume at 4 inches thick as 0.74 cubic yards. a = 12 ft b = 10 ft c = 15 ft s = (12 + 10 + 15) ÷ 2 = 18.5 Area = √(18.5 × 6.5 × 8.5 × 3.5) = 59.8 sq ft At 4 in thick: 59.8 × 4 ÷ 12 = 19.9 cu ft, or 0.74 cubic yards Enter the three sides in the Triangle tab.
Fig. 2 — A triangular pad with sides of 12, 10 and 15 ft. Heron’s formula gives the area from the three sides, so no corner has to be square: 59.8 sq ft, which at 4 in thick is 0.74 cubic yards.

Concrete is sold by the cubic yard (27 cubic feet) for truck delivery, or by the bag for smaller projects.

Slab Formula

Volume = Length × Width × Depth (converted to feet)

Column/Post Formula

Volume = π × (Radius)² × Height

Example: a column 3 ft across and 10 ft tall has a 1.5 ft radius, so π × 1.5 × 1.5 × 10 = 70.7 cubic feet, or 2.62 cubic yards. The usual slip is using the diameter in place of the radius, which overstates the volume four times.

Triangle Formula

Area = √(s × (s − a) × (s − b) × (s − c)), where s = (a + b + c) ÷ 2

This is Heron’s formula: it gives the area of any triangle from its three sides, so no corner has to be square. For sides of 12, 10 and 15 ft, s = 18.5 and the area is √(18.5 × 6.5 × 8.5 × 3.5) = 59.8 sq ft. At 4 in thick that is 59.8 × 4 ÷ 12 = 19.9 cubic feet. That works out to 0.74 cubic yards. For a right-angled corner pad, the two short sides times each other, halved, gives the same area.

Converting to Cubic Yards

Cubic Yards = Cubic Feet ÷ 27

On this page

  1. How to Calculate Concrete Volume
  2. Pre-Mixed Concrete Bag Coverage
  3. How Many Cubic Feet in a Yard of Concrete, and What It Covers
  4. Concrete Yardage by Project Type
  5. Footing Types and Which Mode to Use
  6. How to Pour a Concrete Slab: Step by Step
  7. 7 Concrete Mistakes to Avoid
  8. Concrete Mix & Strength (PSI) Guide
  9. Curing, Weather & When You Can Use It
  10. Everything Else a Slab Needs
  11. Frequently Asked Questions

Pre-Mixed Concrete Bag Coverage

Yields are from the QUIKRETE Concrete Mix data sheet; other brands are close but print their own on the bag.

For projects over 1 cubic yard, consider ordering ready-mix concrete delivered by truck. It's often more cost-effective and ensures consistent quality.

Working purely in bags? Our concrete bag calculator handles every bag size, plus mixing water, pallet counts, and the point where ready-mix becomes cheaper. If you're considering skipping the mixing altogether, read our assessment on the dry pour concrete page first.

How Many Cubic Feet in a Yard of Concrete, and What It Covers

A cubic yard of concrete is 27 cubic feet: a cube 3 ft on every side, weighing about 2 tons. Poured 4 inches thick it covers 81 sq ft, roughly a 9 × 9 ft pad. To turn cubic feet into yards, divide by 27; the cubic yard converter also handles cubic meters and tons. How much area a yard covers depends entirely on slab thickness:

Slab Thickness Area Covered by 1 Cubic Yard
2 inches162 sq ft
3 inches108 sq ft
4 inches81 sq ft
5 inches65 sq ft
6 inches54 sq ft
8 inches40 sq ft

Working backwards from area? Enter your square footage and thickness in the calculator above, or start with our Square Footage Calculator.

How Much Area Do 2, 5, 10 or 15 Yards Cover?

The same arithmetic scaled up, for when you are reading a quote or a ticket rather than planning a pour. Weight uses the calculator's 145 lb per cubic foot, and truckloads assume the roughly 10 cubic yards a full ready-mix truck carries.

Cubic YardsCubic FeetCovers at 4 inCovers at 6 in80 lb BagsWeightTruckloads
12781 sq ft54 sq ft452.0 tonspart load
254162 sq ft108 sq ft903.9 tonspart load
2.567.5203 sq ft135 sq ft1134.9 tonspart load
5135405 sq ft270 sq ft2259.8 tonshalf a truck
10270810 sq ft540 sq ft45019.6 tons1 full truck
143781,134 sq ft756 sq ft63027.4 tons2 trucks
154051,215 sq ft810 sq ft67529.4 tons2 trucks

Coverage is exact geometry with nothing added for waste; the calculator's order line adds your margin on top. The bag column shows why bags stop making sense past a yard or two. A part load usually carries a short-load fee, and both the per-yard price and the short-load threshold vary by supplier, so ask for both when you call.

Concrete Yardage by Project Type

Contractors call the volume of a pour its yardage, and write it CY on an order ticket. Both just mean cubic yards. Whatever the shape, yardage is the volume in cubic feet divided by 27 — what changes from project to project is how you arrive at that volume, which is why the calculator above has a tab per shape.

Project Type What You Measure Volume Formula Worked Example
SlabLength, width, thicknessL × W × T10 × 10 ft at 4 in = 33.3 cu ft = 1.23 CY
Round slabDiameter, thicknessπ × (D ÷ 2)² × T12 ft across at 4 in = 37.7 cu ft = 1.40 CY
FootingTotal length, width, depthL × W × D40 ft of 16 × 8 in = 35.6 cu ft = 1.32 CY
Column or postDiameter, height, countπ × (D ÷ 2)² × H × qtyFour 12 in × 36 in = 9.4 cu ft = 0.35 CY
WallLength, height, thicknessL × H × T20 × 4 ft at 8 in = 53.3 cu ft = 1.98 CY
StepsWidth, rise, run, step countW × rise × run × n(n+1) ÷ 24 ft wide, four 7 × 11 in steps = 21.4 cu ft = 0.79 CY

Every dimension goes into these formulas in feet, so divide inches by 12 before you start — a 4 inch slab is 0.333 ft thick. Forgetting that, or dividing by 3 instead of 27 at the end, accounts for most yardage mistakes. The examples above are the calculator's own output, so you can check it against them.

Why steps take more concrete than people expect

A flight of solid steps has no single thickness, so it is the one shape you cannot do as length × width × depth. Seen from the side it is a staircase: the column of concrete under the bottom tread is one riser tall, the one behind it is two risers tall, and so on to the top. Those columns add up to 1 + 2 + … + n risers, which is n(n+1) ÷ 2.

Four steps therefore hold ten riser-heights of concrete, not four. That gap is why step pours are so often short-ordered. A top landing sits at the full height of the flight, so it adds its own depth times the total rise — adding a 12 inch landing to that same four-step flight takes it from 0.79 to 1.14 CY, almost half again.

The calculator assumes a solid pour, which is the usual case for a poured stoop. If you are filling the core with compacted gravel or rubble and only shelling the treads, subtract that fill volume yourself.

Exact volume vs. what to order

The cubic-yard figure in the results is exact geometry. The order line beneath it adds the waste margin you pick, because subgrade is never perfectly flat and the hole always takes a little more than the arithmetic says. 10% is the usual allowance; go to 15% over a rough or hand-graded base. Running short mid-pour is far worse than having a wheelbarrow left over, because the cold joint where the second batch meets the first is a permanent weak line.

Footing Types and Which Mode to Use

"Footing" covers four different shapes, and the calculator above already handles all of them — they just live under different tabs. This is which tab to pick.

Type What It Is Tab to Use Worked Example
Pad (spread) footingAn isolated square under one post, column or deck pierSlab2 × 2 ft at 12 in = 4.0 cu ft, 0.15 CY each
Strip (continuous) footingA long run under a wall or the perimeter of a buildingFooting40 ft of 16 × 8 in = 35.6 cu ft, 1.32 CY
Sonotube / pierA round column poured in a cardboard formColumn/PostSix 12 in tubes 48 in deep = 18.8 cu ft, 0.70 CY
Thickened-edge (monolithic) slabA slab whose edges are poured deeper as a built-in footing, common under sheds and garagesSlab + Thickened Edge12 × 20 ft at 4 in with a 12 in wide, 12 in deep edge = 120 cu ft, 4.44 CY
Footing + stem wallA strip footing with a short wall built off itFooting plus Wall1.32 + 2.96 = 4.28 CY

Two that catch people out. A pad footing is just a small slab, so it goes in the Slab tab — set How Many to the number of identical pads; if they differ in size, run each size separately and add them. And a sonotube is a column, not a hole: the Column/Post tab takes the tube diameter and how deep it is set, and the quantity field does the rest.

A footing with a stem wall is two pours in one order. Work the footing out under the Footing tab, then the wall on top of it under the Wall tab, and add them — 40 ft of 16 × 8 in footing with a 3 ft stem wall at 8 in thick is 1.32 + 2.96 = 4.28 cubic yards. Ordering only the footing is a common and expensive miss, because the truck is already on site when you find out.

A thickened-edge slab (often called a monolithic slab) pours the footing and the floor in one go: the slab is its normal thickness in the middle and runs deeper in a band around the edge. Volume is the whole slab at its thickness, plus that band taken down the extra depth, with the four corners counted once. A 12 × 20 ft slab at 4 in with a 12 in wide, 12 in deep edge is 80 cu ft of slab plus 40 cu ft of edge, 120 cu ft or 4.44 cubic yards. The edge width and depth are set by your plans or local code, so get them from your local code enforcement office before you form it.

If you are setting posts in individual holes rather than pouring a footing, the post hole calculator subtracts the post itself from the hole, which this page does not.

How big the footing needs to be is not a question this page answers. Width, depth and reinforcement depend on the load, the soil bearing capacity and your local frost depth — they come from a drawing, an engineer, or the table your jurisdiction adopts. Check with your local code enforcement office or building department before you dig; they are the authority that inspects it, and a footing is the one thing you cannot fix afterwards.

How to Pour a Concrete Slab: Step by Step

Pouring concrete is straightforward, but the work happens fast once the truck arrives — so preparation is everything. Here's the full sequence for a typical slab.

  1. Plan and call 811 first. Check local codes and permits, and have underground utilities marked before you dig — it's free and prevents dangerous mistakes.
  2. Excavate and grade. Strip sod and topsoil, then dig to your slab thickness plus about 4 inches for the base. Keep the bottom level and firm.
  3. Add and compact the base. Lay 4 inches of gravel or crushed stone and compact it in thin lifts with a plate compactor. A solid, well-drained base is what stops a slab settling and cracking.
  4. Build the forms. Stake and brace lumber at least as deep as the slab (a 2x6 for a 4 in slab) around the perimeter. Build in a slight slope — about 1/8 to 1/4 inch per foot — so water drains away from structures.
  5. Add reinforcement. Set fiber mesh or #3–#4 rebar on chairs at mid-slab depth. For interior slabs, lay a 6-mil vapor barrier over the base first.
  6. Order or mix the concrete. Aim for a workable 4–5 inch slump. Don't be tempted to add extra water on site — it weakens the mix (see mistakes below). Use our calculator above to order the right amount plus 10%.
  7. Pour and spread. Start at the far corner and work toward your exit. Move concrete with a shovel or come-along and consolidate it into the form corners.
  8. Screed. Drag a straight 2x4 across the top of the forms in a sawing motion to strike off the surface level.
  9. Float. Run a bull float over the surface to fill voids and bring up the paste. Then wait — do not do any further finishing until the bleed water sheen has evaporated.
  10. Edge and cut joints. Round the edges with an edger, then tool or saw control joints (see spacing rule below).
  11. Finish. A broom finish drags texture across the surface for slip resistance — ideal for exterior slabs.
  12. Cure. Keep the surface damp (or use a curing compound) for at least 7 days. Concrete reaches full strength at 28 days.

7 Concrete Mistakes to Avoid

Most concrete failures trace back to a handful of avoidable errors. Watch out for these:

Concrete Mix & Strength (PSI) Guide

Concrete strength is rated in PSI (pounds per square inch) after 28 days of curing. Match the mix to the job:

StrengthBest For
2,500 PSINon-structural fill, some footings
3,000 PSIPatios, sidewalks, general residential slabs
3,500–4,000 PSIDriveways, garage floors, freeze-thaw climates
4,000+ PSIHeavy loads, commercial, structural work

Bagged Mix Types

Bagged concrete makes sense up to about 1 cubic yard. Beyond that, ready-mix truck delivery is usually cheaper and far less work.

What to Specify When You Order Ready-Mix

The plant will ask for more than a yardage. Have these answers ready before you call:

Curing, Weather & When You Can Use It

Curing — keeping concrete moist as it hardens — is what builds strength. Skipping it is a frequent (and invisible) mistake.

How Long Until You Can Use It?

Hot-Weather Pours

In heat, dampen the subgrade, pour early in the day, and cure aggressively — mist the surface or cover it so it doesn't flash-dry and crack. A set retarder buys working time.

Cold-Weather Pours

Only pour when temperatures stay above 40°F, never on frozen ground. Use insulating blankets to hold in the heat of hydration, and consider an accelerator. Protect the slab from freezing for the first few days.

Sealing

After the full 28-day cure, a penetrating or film-forming sealer helps resist stains, de-icing salts, and freeze-thaw damage — reapply every 1–3 years for exterior slabs.

Everything Else a Slab Needs

The concrete is one line of the order. Tick the whole-slab materials options above and the calculator adds the rest, using the same arithmetic as the site’s dedicated calculators. Here is how each line is worked out, using the default 10 × 10 ft slab.

The bag line under the results gives the weight you would be lifting if you mix it yourself. The default slab is 56 bags of 80 lb, which is 4,480 lb to carry, open and mix, and every batch has to go in before the earlier ones start to set. At that size a ready-mix truck is usually less work.

For how each of these goes in, in order, see the step-by-step guide to pouring a concrete slab.

Do It Yourself or Hire a Pro?

Planning ranges for this job, so you can weigh your own time against a crew’s price. They are typical US figures as of 2026, not quotes: prices move with region, season and access, so get at least two local quotes.

JobPlanning Range
Patio-size concrete slab, broom finish, installed$8–$15 per sq ft
Driveway-size slab, broom finish, installed (bigger pours cost less per foot)$6–$12 per sq ft
Breaking out and hauling away an old slab$1–$3 per sq ft
Short-load fee on a small ready-mix order (the threshold varies by plant)$50–$150 per load

At those rates a 10 × 10 ft slab (100 sq ft) comes to roughly $800–$1,500 installed. A pour that small is well under a truckload, so expect a short-load fee on top if the crew orders ready-mix.

When hiring makes sense

  • The pour is bigger than your crew can place and finish in about an hour. Once a truck arrives the clock is running, and a driveway-sized pour realistically needs three or four people who have done it before.
  • The slab carries vehicles or a building. Driveways, garage floors and slabs under a structure need the right thickness, base and reinforcement for the load, and often a permit and inspection.
  • The truck cannot reach the forms, so the concrete has to be pumped or wheeled a long way.
  • You want a decorative finish. Stamping, color and exposed aggregate are skilled work with no second attempt.

The parts you can do yourself

  • Break out and haul away the old slab.
  • Dig to depth, lay and compact the gravel base.
  • Build the forms and place the reinforcement on chairs.
  • Then hire a crew for the pour and finish only. Ask first: many will quote pour-and-finish, but they will want to inspect your base and forms.

What a quote should list

  • Slab thickness and the concrete mix (strength in psi)
  • Base material, depth and how it is compacted
  • Reinforcement: type, size, spacing and how it is held up in the slab
  • Control joints: spacing, depth, and whether they are tooled or sawn
  • Finish, and how the slab is cured afterward
  • Removal and haul-away of anything already there
  • Who pulls the permit and books the inspection, if one is needed
  • What happens if the slab cracks outside the joints or settles

Two quotes that differ a lot usually differ in one of these lines. Ask each contractor to price the same list.

Frequently Asked Questions

Is cement the same as concrete?

No. Cement is one ingredient in concrete. Concrete is the finished building material made by mixing cement with sand, gravel, and water. When people say "cement driveway" they almost always mean concrete.

How much does a yard of concrete weigh?

One cubic yard of concrete weighs roughly 3,700–4,050 pounds — about 2 tons. That's why ready-mix is delivered by heavy trucks and why a solid, compacted base matters so much.

Can I pour new concrete over old concrete?

Yes, if the existing slab is sound (no major cracking or heaving). A bonded overlay should be at least 2 inches thick; thinner resurfacing needs a bonding agent or a sand/topping mix. If the old slab is failing, remove it instead — new concrete will mirror the cracks beneath it.

Do I need rebar or wire mesh?

For a standard 4-inch residential slab, fiber mesh or welded wire mesh is usually enough to control cracking. Use rebar (typically #3–#4 on a grid) for slabs 5 inches or thicker, driveways, or anything carrying heavy loads or built on weak soil.

How long does concrete take to dry and cure?

Concrete is walkable in 24–48 hours, reaches about 70% strength in 7 days, and hits full strength at 28 days. Keep it damp during the first week for the strongest result. People often call it cement drying, but concrete does not harden by drying out: the cement in it reacts with water, which is exactly why keeping the surface moist makes it stronger.

How many cubic feet are in a yard of concrete?

There are 27 cubic feet in one cubic yard of concrete. To convert your project's cubic feet to cubic yards, divide by 27. For example, a 10 × 10 slab at 4 inches thick is 33.3 cubic feet, or about 1.23 cubic yards.

How much concrete do I need for a triangle-shaped slab?

Find the area from the three side lengths with Heron’s formula, then multiply by the thickness in feet. A corner pad with sides of 12, 10 and 15 ft has an area of 59.8 sq ft. At 4 in thick that is 19.9 cubic feet, or 0.74 cubic yards before waste. The Triangle tab in the calculator does this for you.

How many yards of concrete are in a truck?

A fully loaded ready-mix concrete truck holds about 10 cubic yards (most carry 8–11). If you order less than a full truck, expect a "short-load" fee, so it's often worth rounding up small pours or combining work.

What is the minimum a concrete truck will deliver?

There is rarely a hard minimum. Many ready-mix suppliers will send as little as 1 cubic yard, but any order under their short-load threshold carries a short-load fee on top of the per-yard price. That threshold varies by supplier, commonly somewhere from about 3 to 6 cubic yards, so ask for both numbers when you call for a quote. Below about 1 cubic yard, bagged mix is usually cheaper and simpler; the Concrete Bag Calculator compares the two for your volume.

How many bags of concrete make a cubic yard?

Roughly 45 × 80 lb, 60 × 60 lb, 72 × 50 lb or 90 × 40 lb bags. Past about a yard, ready-mix usually costs less; the concrete bag calculator handles every bag size.

How many wheelbarrow loads are in a yard of concrete?

A standard 6-cubic-foot contractor wheelbarrow safely carries about 3 cubic feet of concrete, so one cubic yard is roughly 9 wheelbarrow loads. Smaller 2-cubic-foot barrows take 14 or more loads per yard.

How much extra concrete should I order?

Order 10% extra to account for spillage, uneven ground, and slight measurement errors. Need concrete for fence posts? Try our Fence Post Concrete Calculator.

How thick should a concrete slab be?

4" for sidewalks and patios, 5-6" for driveways, 6-8" for heavy vehicles or RV pads. Try our Patio, Driveway, Sidewalk, or Curb concrete calculators for project-specific estimates.

Can I mix concrete by hand?

For small projects (under 1/3 cubic yard), hand mixing is fine. Larger projects benefit from a mixer or ready-mix delivery.

How much does a yard of concrete cover, in square feet?

A cubic yard is 27 cubic feet, a volume, so the area it covers depends entirely on thickness: about 81 sq ft at 4 inches, 108 sq ft at 3 inches, 65 sq ft at 5 inches, 54 sq ft at 6 inches and 40 sq ft at 8 inches. The formula is 27 ÷ (thickness in feet). Bags, weight and coverage for 1 to 15 yards are in the cubic yard coverage table.

How do I figure out how many yards of concrete I need?

Cubic yards = (length in ft × width in ft × thickness in ft) ÷ 27, with the thickness in inches divided by 12 to get feet. A 20 × 20 ft driveway at 4 inches is 20 × 20 × 0.333 = 133.3 cubic feet, or 4.94 cubic yards; order 5 to 5.5 to allow for subgrade variation. The step people miss is the division by 27: a cubic yard is 27 cubic feet, not 3.

How many yards of concrete do I need for a driveway?

For a typical 20 × 20 ft two-car driveway at the recommended 5 inches, 6.17 cubic yards — call it 6¼. At 6 inches, for trucks or RVs, the same driveway takes 7.41 cubic yards. Enter your own dimensions above for an exact figure.

How much concrete is in a cubic foot?

A cubic foot of concrete weighs roughly 145 lb. If you are mixing from bags, an 80 lb bag yields about 0.60 cubic feet, so a cubic foot takes a little under 1.7 bags. A 60 lb bag yields 0.45 cu ft and a 40 lb bag 0.30 cu ft.

How much area does 15 cubic yards of concrete cover?

15 cubic yards is 405 cubic feet, which covers about 1,215 sq ft at 4 inches or 810 sq ft at 6 inches, and arrives as two truckloads. Other common amounts are in the cubic yard coverage table.

How many cubic yards are in a 3 ft wide, 10 ft tall concrete column?

About 2.62 cubic yards. Use the radius, which is half the diameter: 1.5 ft. π × 1.5² × 10 = 70.7 cubic feet, and 70.7 ÷ 27 = 2.62 cubic yards. Squaring the full 3 ft diameter instead gives 10.5 cubic yards, four times too much. In the calculator's Column/Post tab, both fields are in inches, so enter a 36 in diameter and a 120 in height.

How do I figure square footage for concrete?

Square footage is just length × width in feet — the thickness is not part of it. Break an irregular slab into rectangles, work out each one, and add them together. Our square footage calculator does the splitting for you; bring the total back here with your thickness to get cubic yards.

How much concrete do I need for steps?

Pick the Steps tab and enter the width, the rise and run of a single step, and how many steps there are. A 4 ft wide flight of four 7 × 11 in steps takes 21.4 cubic feet — 0.79 cubic yards, or 36 eighty-pound bags. Add a 12 inch top landing and it rises to 1.14 cubic yards, because the landing sits at the full height of the flight. Steps hold more than people estimate: four steps is ten riser-heights of concrete, not four.

How do I calculate concrete for a footing?

Run the tape around the whole footing and enter that as one total length, then give its width and depth in inches. 40 linear feet of a 16 × 8 in footing is 35.6 cubic feet, or 1.32 cubic yards; a 100 ft perimeter at the same size takes 3.29 cubic yards. How wide and deep your footing has to be is set by your local code, frost depth and soil — take those numbers from your permit set and enter them here, rather than from any calculator.

How much concrete does a round patio need?

Use the Round Slab tab and measure straight across the widest point. A 12 ft circle at 4 inches takes 37.7 cubic feet — 1.40 cubic yards. An 8 ft circle at the same thickness needs only 0.62 cubic yards. Area grows with the square of the diameter, so going from 8 to 12 ft across more than doubles the concrete.

What does CY mean when ordering concrete?

CY is cubic yards, the unit ready-mix is sold in. A ticket reading 3.5 CY means three and a half cubic yards, which is 94.5 cubic feet. Contractors also say yardage for the same thing. Bagged concrete is sold by weight instead, which is why the calculator gives you both a cubic-yard figure and a bag count.

How do I work out concrete from square feet?

Multiply the square footage by the thickness in feet, then divide by 27. A 400 sq ft slab at 4 inches is 400 × 0.333 = 133.3 cubic feet, or 4.94 cubic yards. If you have already measured the area — or added several pours together — use the Total Square Feet tab above and skip the length and width entirely. The shortcut worth remembering is that one cubic yard covers 81 sq ft at 4 inches, so square feet ÷ 81 gives you the yardage directly at that thickness.

Sources & Standards

Estimates for planning only. This calculator sizes material quantities. It does not size structural members, verify load paths, or confirm compliance with the code in your jurisdiction. Local requirements — frost depth, footing sizes, permits, and inspections — override anything here. Check with your local code enforcement office or building department before you build. They are the authority that inspects and signs off the work, they amend the model codes, and what they say overrides any figure on this page. For structural or safety-critical work, have the design checked by a licensed engineer or contractor as well. Dollar figures on this page are typical US planning ranges, not quotes: prices vary by region, supplier and season, so check current local prices before you budget. See our full method and assumptions.

Last updated · How we calculate