πŸ“ The Dig
ft
The dig, not the finished structure — allow working room outside the forms.
ft
Same again: the hole is wider than what goes in it.
ft
Average depth of the cut. Use the deepest point if the ground slopes badly.
Typical ranges. Wet ground and mixed fill vary; override below if you know yours.
%
Overrides the soil type if you set it above zero.
cu yd
A tandem dump truck is commonly 10 to 14 cu yd; a roll-off dumpster is often 10, 20, 30 or 40.
lb/cu yd
Rough guide only — wet soil is far heavier. Set to 0 to skip the weight.
βœ“ Results
Bank Volume (the hole) 22.2 cu yd
Swell Applied +25%
27.8 cu yd
Loose Volume to Haul
Truck or Dumpster Loads 3 loads
Approximate Weight 30.6 tons
Cubic Feet Dug 600 cu ft

Filling the hole back up with stone?

Work out the base material β†’

On this page

  1. The Hole Is Not the Truck
  2. Common Digs
  3. Dig Wider Than You Think
  4. Before the Machine Arrives
  5. Frequently Asked Questions

The Hole Is Not the Truck

Every excavation estimate starts the same way — length × width × depth, divided by 27 — and most of them stop there. That figure is the bank volume: the size of the hole while the soil is still in it.

It is not what you haul away. Undisturbed ground has been compacted by its own weight for a very long time. Dig it and it breaks into lumps with air between them, and it takes up appreciably more room than the hole it came out of.

A 20 × 10 ft dig 3 ft deep is 600 cubic feet — 22.2 bank cubic yards. In common earth that comes out as roughly 27.8 loose cubic yards. The extra 5.6 yards is not an error; it is the air you just introduced, and you are paying to move it.

SoilTypical SwellBankLooseLoads at 10 cu yd
Sand or gravel15%22.2 cu yd25.6 cu yd3
Common earth or loam25%22.2 cu yd27.8 cu yd3
Clay35%22.2 cu yd30.0 cu yd3
Blasted rock55%22.2 cu yd34.4 cu yd4

Swell percentages vary with the soil and with how wet it is; these are typical figures and the calculator lets you override them. What does not vary is the direction — it always swells, and the spoil pile is always bigger than you expected.

Common Digs

Bank and loose volumes at 25% swell, with loads at a 10 cu yd truck. Every figure is this calculator's own output:

JobBank VolumeLoose VolumeLoads
Paver patio, 10 × 10 ft at 8 in2.5 cu yd3.1 cu yd1
Driveway, 12 × 50 ft at 10 in18.5 cu yd23.1 cu yd3
Shed pad, 12 × 16 ft at 8 in4.7 cu yd5.9 cu yd1
Footing trench, 60 ft × 2 ft at 3 ft13.3 cu yd16.7 cu yd2

The patio row is the one that surprises people. An 8 in dig over 100 sq ft does not sound like much until 3 cubic yards of it is sitting on the driveway — roughly a small trailer, or a pile about 10 ft across and waist high.

Dig Wider Than You Think

Two things make the hole bigger than the drawing, and both get left out of estimates.

Working room. You cannot set a form, strip it, or run a compactor with no space to stand. Allow 6 to 12 in beyond the finished face, more where someone has to work in the trench. On a 20 × 10 ft dig, an extra 6 in all round is about 15% more spoil — and it is spoil you will definitely produce, so it belongs in the estimate rather than as a surprise.

Slope and over-dig. Ground is rarely level, and a machine operator cuts to the deepest point rather than the average. If the fall across the site is significant, measure the depth at several points and use the deeper figure; being over on spoil costs a part-load, being under costs a second mobilization.

Before the Machine Arrives

Frequently Asked Questions

How do I calculate excavation volume?

Length × width × depth in feet, divided by 27. A 20 × 10 ft hole 3 ft deep is 600 cubic feet, or 22.2 cubic yards. That is the bank volume — the size of the hole. It is not how much soil you end up moving, because soil expands the moment you dig it.

What is soil swell?

Undisturbed ground is compacted by its own weight and by time. Dig it and it breaks into lumps with air between them, so it takes up more room — typically 25% more for common earth, and more for clay. Published clay figures range from about 25% (Caterpillar Performance Handbook) to 40% (US Army FM 5-434, which lists sand and gravel at 10–15% and loam at 15–35%); the calculator uses 35% for clay as a middle figure, so test a load if the number matters. That 22.2 cu yd hole yields about 27.8 cu yd of loose spoil. Every load you haul is measured in loose yards, not hole yards.

Why does my dirt not fit back in the hole?

Because of the same swell, in reverse. Spoil that came out of a hole will not go back into it without being compacted, and even then you will usually have material left over — backfill compacted in lifts ends up denser than the loose pile but rarely as dense as undisturbed ground. Plan on hauling some away even on a job you think is balanced.

How many truckloads is my excavation?

Divide the loose volume by the truck capacity, not the bank volume. At 27.8 loose cu yd and a 10 cu yd truck that is 3 loads. Using the 22.2 cu yd hole figure would have suggested 3 as well here, but on a bigger dig the swell is what adds the extra trip — and a trip is usually priced whole.

How much does a cubic yard of dirt weigh?

Very roughly 2,000 to 2,400 lb loose for common earth, more for clay and much more when wet — water is heavy and soil holds a lot of it. It matters because weight, not volume, is usually what limits a truck: a tandem may be rated for more cubic yards than it can legally carry in wet clay. Treat the weight figure here as a guide and ask your hauler.

Should I dig wider than the structure?

Yes, and people routinely forget to allow for it. You need working room to set forms, strip them, and get a compactor into the trench — commonly 6 to 12 in beyond the finished face, more where someone has to stand in there. That extra ring is real volume: on a 20 × 10 ft dig, an extra 6 in all round adds about 15% to the spoil.

Do I need to call before I dig?

Yes, every time, and it is free. Call 811 in the US a few working days ahead and the utilities mark their buried lines. Hitting a gas or electric service is dangerous and expensive, and hitting a fiber line is merely expensive. Permits and any shoring requirements are a separate matter — check with your local code enforcement office before the machine arrives.

How deep can I dig without shoring?

That is a safety question with a legal answer, and it is not one a calculator should give you. Trench walls collapse without warning and the depth at which protection becomes mandatory, plus what counts as adequate protection, is set by regulation and by soil classification. Before digging anything you intend to enter, check the requirements with your local code enforcement office and the relevant safety authority.

Is a dumpster or a dump truck cheaper?

It depends on the volume and on access. A roll-off dumpster sits on site and you fill it at your own pace, which suits a job spread over days — but it takes a parking space and often a permit. A dump truck is faster and usually cheaper per yard once you are past a couple of loads, provided a truck can get to the spoil. Clean fill sometimes goes free to a site that wants it, which beats both.

How much spoil comes off a 10 x 10 ft patio dig?

At a typical 8 in excavation, 100 sq ft × 0.67 ft is 67 cubic feet, or 2.5 bank cubic yards — about 3.1 loose cubic yards once it swells. That is roughly one small trailer load, and it is the figure people underestimate most often, because a patio dig looks shallow until it is in a pile on the drive.

Can I use the spoil as fill elsewhere?

Topsoil, yes, for garden beds and regrading — it is the most valuable thing coming out of the hole and it is worth stripping and stockpiling separately before you dig the rest. Subsoil and clay are poor structural fill and should not go back under anything you intend to build on unless it is placed and compacted in lifts to a spec. Mixed spoil with roots and rubble is not fill at all.

What about the base material going back in?

That is a separate order, and it does not offset the spoil — the hole gets filled with something better than what came out. Work the stone out on the gravel calculator, which also handles the compaction allowance, since you buy loose stone and measure a compacted depth.

Sources & Standards

Estimates for planning only. The figures here follow published model codes and industry standards, but those are adopted and amended locally, and older buildings are often legally exempt from the current edition. Check with your local code enforcement office or building department before you order or build β€” they are the authority that inspects the work, and what they require overrides anything on this page. See our full method and assumptions.