📐 Pitch and Span
in
How far the roof climbs over the run below. A "6/12 roof" rises 6 in.
in
Almost always 12 — pitch is quoted per 12 in of horizontal run.
degrees
Know the angle instead? Put it here and it overrides the rise and run.
ft
Wall to wall, for the rafter length. A gable rafter spans half of this.
in
Horizontal projection past the wall. The rafter has to cover it too.
✓ Results
Pitch 6 in 12
26.6°
Angle from Horizontal
Slope Factor 1.118
Grade 50%
Rafter Length (incl. overhang) 19.0 ft
Roof Covering above the 4:12 threshold

Got the pitch? Turn it into shingles.

Use the roofing calculator →

On this page

  1. What Pitch Tells You
  2. Rafter Length from the Pitch
  3. Pitch, Coverings and Whether You Can Stand On It
  4. Where This Page Stops
  5. Frequently Asked Questions

What Pitch Tells You

A pitch written 6/12 means the roof climbs 6 inches for every 12 inches it travels horizontally. The second number is nearly always 12, because that is the convention — rise per foot of run.

From that one ratio, three useful numbers follow:

The angle relationship is not linear, which is the part that surprises people. Going from 6/12 to 12/12 doubles the pitch but takes the angle from 26.6° only to 45°, not to 53°.

A useful sanity check: 12/12 must come out at exactly 45° and a slope factor of √2 ≈ 1.414. Any pitch tool that disagrees is wrong.

Rafter Length from the Pitch

Rafter length is the horizontal run multiplied by the slope factor. For a gable roof the run is half the building width, plus the overhang, because the rafter has to carry that too.

A 32 ft wide building with a 12 in overhang: half the width is 16 ft, plus 1 ft of overhang, is 17 ft of horizontal run. At 6/12 the slope factor is 1.118, so the rafter is 17 × 1.118 = 19.0 ft.

Buy the next stock length up. The plumb cut where the rafter meets the ridge and the birdsmouth where it sits on the wall plate both consume length, and neither is in the 19.0 ft figure — that is the theoretical line length from the wall to the ridge.

Rafter size is a different question from rafter length. How deep the member needs to be depends on the span, the spacing, the species and the snow load, and it comes from a span table in your local code or from an engineer. This page gives you the length to buy, not the size to use.

Pitch, Coverings and Whether You Can Stand On It

Pitch decides two practical things before it decides anything aesthetic: what you are allowed to cover the roof with, and whether anyone can work on it.

PitchCategoryAsphalt ShinglesWorking On It
1:12 – 2:12Low slopeNot permitted for asphalt shingles below 2:12Membrane or low-slope metal
2:12 – 4:12LowShingles allowed with double underlaymentEasy to walk
4:12 – 6:12ConventionalStandard shingle applicationWalkable in dry conditions
7:12 – 9:12SteepStandard applicationRoof brackets or a harness
10:12 and upVery steepStandard applicationNot walkable — staging required

The 2:12 and 4:12 thresholds are code figures, not preferences. The IRC permits asphalt shingles down to 2:12, and requires a double layer of underlayment from 2:12 up to 4:12. Below 2:12 shingles are not an option and the roof needs a membrane or a low-slope metal system. Jurisdictions amend the model code, so confirm the figures with your local code enforcement office before you frame a low roof — changing the pitch afterwards is not a repair, it is a rebuild.

The walkability column is about cost as much as safety. Past about 6/12 the same square footage takes appreciably longer, and past 10/12 it needs staging, which turns up as a line on the quote.

Where This Page Stops

Three neighboring questions, each with a better home:

Frequently Asked Questions

What does a 6/12 roof pitch mean?

The roof rises 6 inches for every 12 inches it travels horizontally. Pitch is always quoted per 12 in of run, which is why the second number is nearly always 12. A 6/12 roof sits at 26.6° from horizontal and has a slope factor of 1.118 — meaning the roof surface is 11.8% larger than the footprint underneath it.

How do I convert roof pitch to degrees?

Take the arctangent of rise divided by run. A 4/12 roof is arctan(4 ÷ 12) = 18.4°, a 6/12 is 26.6°, and a 12/12 is exactly 45°. The relationship is not linear, which catches people out: doubling the pitch from 6/12 to 12/12 does not double the angle, it goes from 26.6° to 45°.

What is the slope factor?

The number you multiply a footprint by to get the actual roof surface: √(1 + (rise ÷ run)²). For 6/12 that is √1.25 = 1.118. It exists because a roof is a tilted plane — the surface is always longer than the plan area beneath it, and the steeper the roof the bigger the gap. To go from a footprint to shingles, use our roofing calculator, which applies it for you.

How do I calculate rafter length?

Multiply the horizontal run by the slope factor. For a gable roof the run is half the building width, plus any overhang. A 32 ft wide building with a 12 in overhang gives 16 + 1 = 17 ft of horizontal run; at 6/12 that is 17 × 1.118 = 19.0 ft of rafter. Buy 20 ft stock — the plumb cut at the ridge and the birdsmouth both consume length.

What is the minimum roof pitch for shingles?

The IRC figure for asphalt shingles is 2:12, and between 2:12 and 4:12 a double layer of underlayment is required. Below 2:12 asphalt shingles are not permitted at all and the roof needs a membrane covering instead. These are the model-code figures — your jurisdiction amends them, so confirm with your local code enforcement office, which is the authority that inspects the roof.

What roof pitch is walkable?

Up to about 6/12 most people can work on a dry roof in good boots. 7/12 to 9/12 is uncomfortable and wants roof brackets or a harness. 10/12 and steeper is not walkable — it needs staging, and the material has to come up to you. This matters for estimating labor as much as safety: the same square footage takes far longer on a steep roof.

Is pitch the same as slope or grade?

Not quite, and the three get mixed up constantly. Pitch here means rise per 12 of run, written 6/12. Slope is used interchangeably in US roofing. Grade is the same ratio as a percentage — a 6/12 roof is a 50% grade, because 6 ÷ 12 = 0.5. Confusingly, "pitch" in some older texts means rise over the total span rather than over 12, which halves the number.

How do I measure the pitch of an existing roof?

The safest way is from inside the attic: hold a level horizontally against a rafter, mark 12 in along it, and measure straight up from that mark to the rafter’s underside. That measurement is your rise. You can also do it from a ladder at the gable end, or with a phone app against a rafter. Our roof measuring guide walks through the whole process, facet map included.

Why is a 12/12 roof exactly 45 degrees?

Because rise and run are equal, so the triangle is isosceles and the angle is arctan(1) = 45°. It is the one pitch you can check without a calculator, and it is a useful sanity check on any pitch tool — if 12/12 does not come out at 45°, something is wrong. Its slope factor is √2, about 1.414, so a 12/12 roof has 41% more surface than its footprint.

Does a steeper roof cost more?

Yes, twice over. It has more surface area for the same footprint — a 12/12 roof is 41% larger than the plan, against just 5% for a 4/12 — and past about 6/12 it stops being walkable, so labor slows down and staging costs appear. A steep roof also sheds water and snow better and gives usable attic volume, which is why people accept the cost.

What pitch do I need for a shed or porch roof?

Enough to drain, and enough for whatever covering you intend to use — which is the constraint people hit. A low shed roof at 1:12 cannot take asphalt shingles at all, and from 2:12 up to 4:12 they are allowed only over a double layer of underlayment; below that it needs a membrane or a standing-seam metal system rated for low slope. Decide the covering and the pitch together, and check the covering’s minimum slope with your local code enforcement office before you frame it.

How many shingles will my roof need?

That is a different question and it has its own page — the roofing calculator takes your footprint and pitch and returns squares, bundles, underlayment and drip edge. This page converts the pitch itself; that one spends it.

Sources & Standards

Estimates for planning only. The figures here follow published model codes and industry standards, but those are adopted and amended locally, and older buildings are often legally exempt from the current edition. Check with your local code enforcement office or building department before you order or build — they are the authority that inspects the work, and what they require overrides anything on this page. See our full method and assumptions.

Last updated · How we calculate